Health check
A free schedule review, without obligation. Send us your P6 programme and we’ll tell you where its logic, constraints and float put completion at risk, and what to fix first.
| Check | Result | Target | Status |
|---|---|---|---|
| Missing logic | 2.1% | ≤ 5% | Pass |
| Leads (negative lags) | 0 | 0 | Pass |
| Lags | 9.0% | ≤ 5% | Review |
| Finish-to-start links | 93% | ≥ 90% | Pass |
| Hard constraints | 7.4% | ≤ 5% | Review |
| High float (over 44 days) | 18.2% | ≤ 5% | Review |
| Negative float | 0 | 0 | Pass |
| High duration (over 44 days) | 3.1% | ≤ 5% | Pass |
| Critical path test | Passed | Pass | Pass |
Fix first: 95 hard constraints override the logic, 6 of them on the critical path.
Send your schedule
File too large? Send the form without it and email the file to arnold@planner-link.com. Your schedule is treated as confidential and used only for this review.
What we check
- Missing logic and open ends
- Leads, lags and relationship types
- Hard constraints that override logic
- High float and negative float
- Long-duration activities
- Invalid dates and out-of-sequence progress
- Critical path continuity
- Baseline and progress performance
Based on the DCMA 14-point assessment, read by a planner rather than a script.
What you get
A short written summary: what is healthy, what is risky and what to fix first. If it helps, we talk it through with you on a call.
Rather talk first?
Tell us about the project, the challenge, where it is and when you need support. We'll come back with the most practical next step.
Your message goes straight to PlannerLink. We reply by email or phone, whichever you prefer.
Direct lines
- South Africa+27 79 904 3157
- Australia+61 456 982 689
- Emailarnold@planner-link.com